Project Experience
BURLINGTON RESOURCES Install Inconel lined pipeline to hook up sour
gas wells.
WY
WILLIAMS PRODUCTION Coal Bed Methane projects near Gillette, Wyoming.
Install 2” thru
12” PE gas and water piping. Install electrical cable. Set and hook
up POD buildings and skid mounted compressors on yearly contract. Also, several
12” road bores.
WY
JACOBS RANCH MINE Remove 8 miles of 4” pipelines for mine expansion.
WY
KANEB PIPELINE Pipeline reconditioning near Mule Creek Junction. WY-SD
DEVON ENERGY Build reservoirs & approximately 15 miles of roads
near Wright. WY
KINDER-MORGAN Retire and reclaim 4 miles of pipelines at Jacobs Ranch
Mine.
WY
ENCANA Install 36,000’ of 8” pipeline on Grass Mesa. Co
SHELL OIL Abandon 4 miles of 4” pipeline. Wy
BELLE FOURCHE PL Install 6 miles of 6” PL. Wy
EOG Install 10 miles of 4” zaplok & welded pipeline at Allemand
Ranch.
Wy
BELLE FOURCHE PL Hook up storage tanks at Donkey Creek. Wy
QUESTAR GAS MANAGEMENT Constructed compressor station and support piping
and equipment.
WY
WILLIAMS PRODUCTION Coal Bed Methane projects near Gillette, Wyoming. Install
2” thru
12” PE gas and water piping. Install electrical lines. Set and hook
Up POD buildings and Skid mounted compressors. Yearly Contract.
WY
BURLINGTON RESOURCES Install Inconnell lined pipeline to hook up sour gas wells.
WY
QUESTAR EXPLORATION AND PRODUCTION
Install 2 miles of 3” steel pipeline.
WY
KINDER MORGAN Remove heat exchanger from the Douglas Plant.
WY
KANEB PIPELINE Re-condition 6” steel pipeline near Edgemont, South Dakota.
Replace corroded sections.
SD
BELLE FOURCHE PIPELINE 8” Steel re-conditioning project from Recluse
to Donkey Creek.
WY
QUESTAR GAS MANAGEMENT Build and install Slug Catcher at the Black’s
Fork site.
WY
KINDER MORGAN Re-located (3) Compressors, Buildings, Support Piping and retired
6”, 8” and 10” pipeline.
WY
SHELL OIL 16” Pipeline Re-conditioning project. Smart pig remediation.
Install sleeves at various locations from Ft. Laramie to Osage.
WY
EXCO RESOURCES Install 3 miles of poly.
WY
BELLE FOURCHE Install Lac Unit, (6) Tank battery, Transfer Unit in North Dakota.
ND
QUESTAR GAS MANAGEMENT Install by pass valve in the Pinedale Compressor
station. Hot taps.
WY
DRAKE CONTRACTORS Install 2 miles of poly at Warren Air Force Base in Cheyenne.
WY
BELLE FOURCHE Install 5.5 miles of 6” steel including Road Bores and
Railroad Bore
near Wright.
WY
SHELL OIL Nitrogen Puge oil and abandon Amos Draw gathering field near Gillette.
WY
SHELL OIL Repair wash outs and install erosion control near Reno Station.
WY
BELLE FOURCHE Clean up oil spill.
WY
BELLE FOURCHE Install diesel fuel facility at yard in Gillette.
WY
DEVON ENERGY Build Ponds, install overflows, and build POD pads near Wright.
WY
BELLE FOURCHE Install 3 miles of 4” steel gathering lines near Douglas.
WY
|