| BURLINGTON RESOURCES | Install Inconel lined pipeline to hook up sour gas wells. |
| WILLIAMS PRODUCTION | Coal Bed Methane projects near Gillette, Wyoming. Install 2” thru 12” PE gas and water piping. Install electrical cable. Set and hook up POD buildings and skid mounted compressors on yearly contract. Also, several 12” road bores. Coal Bed Methane projects near Gillette, Wyoming. Install 2” thru 12” PE gas and water piping. Install electrical lines. Set and hook Up POD buildings and Skid mounted compressors. Yearly Contract |
| JACOBS RANCH MINE | Remove 8 miles of 4” pipelines for mine expansion. |
| KANEB PIPELINE | Pipeline reconditioning near Mule Creek Junction. Re-condition 6” steel pipeline near Edgemont, South Dakota. Replace corroded sections. |
| DEVON ENERGY | Build reservoirs & approximately 15 miles of roads.
Build Ponds, install overflows, and build POD pads near Wright. WY |
| KINDER-MORGAN | Retire and reclaim 4 miles of pipelines at Jacobs Ranch Mine. Remove heat exchanger from the Douglas Plant. Re-located (3) Compressors, Buildings, Support Piping and retired 6”, 8” and 10” pipeline. |
| ENCANA | Install 36,000’ of 8” pipeline on Grass Mesa. |
| SHELL OIL | Abandon 4 miles of 4” pipeline. 16” Pipeline Re-conditioning project. Smart pig remediation. Install sleeves at various locations from Ft. Laramie to Osage. Nitrogen Puge oil and abandon Amos Draw gathering field near Gillette, WY Repair wash outs and install erosion control near Reno Station. |
| BELLE FOURCHE | Install 6 miles of 6” Poly. Hook up storage tanks at Donkey Creek. Wy 8” Steel re-conditioning project from Recluse to Donkey Creek, WY Install Lac Unit, (6) Tank battery, Transfer Unit in North Dakota. Install 5.5 miles of 6” steel including Road Bores and Railroad Bore near Wright, WY Clean up oil spill. Install diesel fuel facility at yard in Gillette, WY Install 3 miles of 4” steel gathering lines near Douglas. WY |
| EOG | Install 10 miles of 4” zaplok & welded pipeline at Allemand Ranch |
| QEP | Constructed compressor station and support piping and equipment. Install 2 miles of 3” steel pipeline. Build and install Slug Catcher at the Black’s Fork site. Install by pass valve in the Pinedale Compressor station. Hot taps. |
| EXCO RESOURCES | Install 3 miles of poly. |
| DRAKE CONTRACTORS | Install 2 miles of poly at Warren Air Force Base in Cheyenne, WY |
Northwinds of Wyoming, Inc | Douglas, Wyoming 82633 | 307-358-6550